Concrete roof tiles are a “main concern” with “lead times averaging 24-30 weeks”

by Jennie Ward

CLC’s latest statement on Construction Product Availability states “while many factors could still cause disruption, we are currently in a better position than three to four months ago”, but points to concerns with transport issues and other materials including concrete roof tiles.

In their latest statement on construction product availability, John Newcomb, CEO of the Builders Merchant Federation and Peter Caplehorn, CEO of the Construction Products Association – both co-chairs of the Construction Leadership Council’s Product Availability working group have stated “the supply chain is just about managing under unprecedented circumstances” but pointed to concrete roof tiles as a “main concern” with lead times of 24-30 weeks.

In their statement on the Construction Leadership Council’s website published on 21st September, they explained: “While there has been a slight levelling off in construction demand, mostly in the domestic Repair, Maintenance and Improvement sector, demand remains high, with strong projections based on the anticipated pipeline of work for the rest of the year.

“Overall product supply has improved slightly with lead times stabilising in some product areas. That said, certain items – timber battens, chipboard, steel lintels and PVC products – remain in short supply.

“The main concerns are around bricks and blocks, with some regions experiencing increased delays in securing supplies; concrete roof tiles, where lead times are averaging 24-30 weeks, and bagged cement. There was some easing in the shortages of bulk and bagged cement in August, with additional cement brought from abroad; however, delivery has been particularly constrained by the lack of domestic haulage capacity. Extended delivery times will therefore likely continue until the end of the year and some allocation will likely remain in place.

“Transport issues continue to be the most common and pressing concern across the supply chain. Global shipping capacity has been reduced by 25% since the start of the pandemic, leading to delays and high container prices, and there is little sign of relief as we head into the Christmas season. The British Ports Association expects challenges to continue until at least the second quarter of 2022.

“Within the UK, the shortage of HGV drivers is affecting every sector and will take many months to resolve, despite Government action to increase driver testing. This is a major contributor to delayed deliveries in all construction product areas; one manufacturer reported ‘factories piled with product that we cannot get out’.

“The level of price increases for many products has moderated but this may be short-lived, due to continued pressure on costs of raw materials, labour and transport. Energy prices, particularly the doubling of the wholesale cost of gas, is also a critical factor for manufacturers, along with higher carbon prices related to the increased use of coal-fired power stations. This is likely to be exacerbated following a fire at a power facility in Kent shutting down a crucial link between the British and French power grids.“Despite the current challenges, by working closely and collaboratively, the supply chain is just about managing under unprecedented circumstances. We are not out of the woods yet. While many factors could still cause disruption, we are currently in a better position than three to four months ago.”